Brief

Fabrication and installation of pipework on the interior and exterior of a storm tank. Due to the adverse weather experienced during late 2013 the original tank collapsed completely. This meant that the tank had to be rebuilt and all pipework replaced. This was a time limited project and we had to meet a strict deadline.

What we did

K&G were given drawings which illustrated the intended design of the pipework, it was vital for us to attend site to take our drawings to ensure accuracy.

We sent out project engineer to site on the same day of the enquiry. Getting the drawings ready for the following day we were able to order the pipe work. When we received the pipework it was TIG welded together and cut to size based on our drawings.

Transporting the pipe work to site and installation took place within the agreed time frame and our engineers installed the pipe work to the correct specifications.

All pipework was installed and attached to the pump, valve and tank already in situ.

Outcome

The pipework was completed and we were able to deliver an important aspect of the customers overall job whilst maintaining high health and safety standards as well as exactly matching the customers initial request, staying within agreed timeframe and budget.